2024 Submittal Procedure


EMPC Schedule for Submittals

GENERAL INFORMATION:

All materials proposed for use in concrete and all concrete mix designs shall be approved by the Eastern Missouri Pavement Consortium (EMPC) prior to use. Such materials include coarse and fine aggregates, cementitious materials, admixtures, and water. All materials (except as noted below) shall be SAMPLED and TESTED after October 1st of the previous year; the most current testing data is ANNUALLY tested by MoDOT or as written in the specification. For coarse aggregate ACR test procedures only, tests must be within 12 months of the material test date. No testing shall be used for more than one EMPC year.

All EMPC-approved mix designs for the 2023 EMPC year will expire on April 1, 2024, even if mixes are used on multi-year construction projects. New mix designs must be submitted to GBA to remain an approved EMPC supplier for 2024. Mix designs meeting specification requirements in PDF format, received by February 23, 2024, will be approved by the deadline. 

EMPC will preapprove aggregates and cementitious materials. Submit certifications directly to EMPC. If EMPC approves the material, it will be added to the website as an option.


FEES:

Concrete Materials:

$130 fee per material
 

Concrete Mix Designs:

$140 fee per mix design when received before March 1, 2024
$190 fee per mix design when received after March 1, 2024
$300 fee per mix design requiring approval in less than ten working days received at any time
Note: An additional $190 fee will be assessed for each mix design requiring a second round of comments and $190 for any additional round of comments.
 
GBA will not review any submittals prior to receiving payment. GBA does not accept credit cards. 
 
Make all checks payable to “GBA” and send them to the following address:

Attn: Josh Miller

GBA

9801 Renner Blvd. #300

Lenexa, KS 66219

 
If you are submitting close to the April 1st deadline, please send checks prior to submitting to avoid delays in review. If your company requires an invoice prior to payment, send a request for an invoice prior to submittal.

All mix designs shall be submitted through the website using the current Mix Design Submittal Form on www.empcpavement.org.

Strength tests will be the first item reviewed in any submittal.

Mix designs with incomplete or incorrect strength tests will be returned without further review of the mix design. This will count as the first round of comments.

All mix designs are good for one year and must follow the current EMPC Concrete Material Specification.


SUBMITTAL REQUIREMENTS:

Concrete mix design submittals shall include:

A minimum of three compressive strength tests shall be performed by a qualified laboratory. A strength test is defined in Article 26.12.1.1 of ACI 318-14. Test strengths shall meet or exceed the required average strength as shown below.

Compressive strength test results (strength tests) are required for each mix design submitted. However, if mix designs differ only in water-to-cement ratio, compressive strength test results for the highest water-cement ratio will be acceptable in all mix designs of the series. Strength tests shall be on concrete that contains materials, sources, ratios, admixtures, and admixture dosages consistent with the submitted mix design and shall meet the current specification requirements. For currently approved mix designs, each strength test shall have been completed after the most recent approval date (except as noted below). For new mix designs, strength tests shall have been completed within the previous 12 months.

An example of an acceptable test is as follows:

Please contact the EMPC administrator prior to casting cylinders if you have any questions.

Each strength test shall represent concrete from separate batches that include all the water, cement, and non-optional admixtures in the design. The following shall be provided with each strength test:

The average of the strength tests shall meet or exceed the required average compressive strength as determined by ACI 301-16, Article 4.2.3, with the following modification:

At least one-half of the tests used to determine the standard deviation under Article 4.2.3.1 shall be on strength tests performed after the previous year’s approved mix design date. No test shall be more than two years older than the previous year’s approved mix design date.  Documentation showing the standard deviation and all other relevant calculations shall be provided.

Strength test results prior to 28 days are acceptable if they meet all other requirements. 

Aggregates and Cementitious Material Submittals shall include (Online Form and Attached PDF Format):

The ready-mix supplier shall provide testing results for ASTM C 1567 Mortar Bar Expansion. Expansion shall be a maximum of 0.10% at 16 days.

Designated fine aggregate may be substituted for the same source of fine aggregate without the standard testing required in a mix design. A mix design must be submitted for both options.

Mix designs shall be approved for the EMPC year: April 1, 2024, through March 31, 2025.


Please send all submittal information through the website. Contact the EMPC administrator with questions.

Gary Whiteside
George Butler Associates, Inc.
gwhiteside@gbateam.com
Tel. 636.385.5659
 
Josh Miller
George Butler Associates, Inc.
jmiller@gbateam.com
Tel. 913.577.8254